User guide ProjectWork

Panels

ProjectWork online project management software shows all project information from left to right in separate panels. Each panel has its own menu.

panels : Capacity | Resources | ProjectWork | Tasks | Gantt

  • The Capacity panel contains a bar chart showing the allocation of resources over time.
  • The Resources panel contains a table with the resources of the project.
  • The ProjectWork panel contains general information, a dialog of a function or detailed information from a selected task or resource.
  • The Tasks panel contains a table with the tasks of the project.
  • The Gantt panel contains a bar chart showing the tasks over time.

Tasks, resources and task/resource assignments are visible in the panels. Panels can be hidden to give other panels more space.

The ProjectWork panel is the central panel that contains on top the filename and below the default dialog or temporary dialogs of various functions. After closing a temporary dialog the default dialog returns.

When the filename is clicked the Properties dialog appears where you can change the file name in Google Drive. Beneath the filename is room for a status message regarding automatic and manual storage in Google Drive. When you make a change to the view, like expand/collapse or filter, a message to save the view appears. If you click the message, the view is saved in the schedule file and the view synchronizes to all active users.

The ProjectWork panel with default dialog:

file name
Google Drive status message
Save view in Google Drive


Google account and the option to sign out
trial status and license ordering with PayPal


shortcuts to menu functions, like Properties and Settings
option to mark rows that change when you or someone else make a change in the schedule


help like manual, videos and helpdesk
built-in tooltip quick tour and assistance dialog

Edit schedule

The Tasks and Resources tables can be edited per cell by clicking the cell. An outline appears around the cell and the row gets selected. The text can now be entered.

The Enter key advances the selection to the cell below, the Shift + Enter to the cell above.
The Tab key advances the selection to the cell on the right, Shift + Tab to the cell on the left.

Copying a cell to multiple cells with the same text at once starts by selecting a cell with the left mouse key followed by selecting this cell and adjacent cells above or below with the Shift key pressed. After releasing the mouse the cells get the same text as the first selected cell, see example below.

With copy (Ctrl + C) and paste (Ctrl + V) you can copy text quickly from a spreadsheet or document into ProjectWork. Multiple cells from a column of the spreadsheet or multiple rows of text from the document will paste in a ProjectWork column in subsequent rows. When copying for new tasks, start with the Task description column. When copying dates, make sure that the date format setting in ProjectWork matches the date format of what you copy.

When a single task/resource row is selected a task/resource dialog appears to see and edit the details. Hidden columns are also visible here. Next to the dialog the quantity column shows the assigned quantity which can be edited as well.

Select rows

Some menu items work in combination with one or more selected rows in the Tasks or Resources table. If no row is selected, these items are grayed out and cannot be used. Selected rows have a dark background color.

Rows can be selected by selecting a row and with left mouse key pressed selecting neighboring rows.

Another way of selecting consecutive rows is by selecting the first row and with Shift pressed the last row.

De-selecting is done with the ESC key.

Arrange columns

This dialog is opened from the ProjectWork Tasks menu or the ProjectWork Resources menu. It can also be opened by clicking on the Tasks or Resources table header. The width of a column can be resized by dragging the border in the column header. By clicking the border the column width is automatically resized to its contents. The width of the columns can be manually saved.

Columns can be arranged in a dialog by clicking on the column headers or from the panel's menu. A checked column is visible. The order can be re-arranged by dragging a column and dropping it at the requested position. The view of the columns can be manually saved.

One custom column at a time can be added with Apply. Adding a column is done by giving it a title and type. The column appears as last and can be repositioned by dragging it to the requested position. A custom column can be removed by deleting its title.

Keyboard shortcuts

Keyboard and mouse can perform some functions directly, see list.
Mac: ⌘-command key instead of Ctrl.

Ctrl + Mouse click Link or unlink selected task(s) with the clicked task
Assign selected resource(s) to clicked task
Ctrl + Scroll wheelZoom in/out in Gantt and Capacity chart
Shift + Scroll wheelHorizontal scroll in panel
Right mouse click
Mac: Ctrl + Mouse click
Context menu
EscDeselect and close dialogs
TabNext cell
Shift + TabPrevious cell
EnterNext row
Shift + EnterPrevious row
Shift + Mouse clickSelect rows between selected row and clicked row
Shift + Mouse pressedCopy content of selected cell to cells below/above
Ctrl + LReload project
Ctrl + ZUndo
Ctrl + YRedo
Ctrl + CCopy row(s)
Ctrl + XCut row(s)
Ctrl + VPaste row(s)
Ctrl + UInsert row(s) above
Ctrl + DInsert row(s) below
Ctrl + EErase row(s)
InsInsert row(s) above
DelDelete row(s)
Ctrl + >Indent row(s) more
Ctrl + <Indent row(s) less
Ctrl + ?Show keyboard shortcuts
mouse click on headersArrange columns

Context menu

The context menu appears by first selecting one or more rows and then right mouse-click (Mac: Ctrl + Mouse click) the rows. The selected function affects the selected row(s).

Dropdown menu

New project

Starts a new project with an adjustable title. The file is put in Google Drive in the same folder(s) as the original. Sharing permissions are not copied from the original file, but they are copied from the common folder(s).

Open project...

Shows a list from Google Drive with previously saved ProjectWork files. Opens the selected file.

Make a copy...

Opens a dialog to copy the schedule to a new file which opens in a new browser tab. The name can be changed in the copy afterwards.

The copying has options, that are enabled if the data is present:
- copy also the published spreadsheet and link it to the copy, keeping the layout of the original,
- keep the copy linked to the same dashboard spreadsheet as the original,
- copy the saved clipboard tasks in the schedule,
- copy the baselines in the schedule.

Overwrite file...

Opens a list from Google Drive with previously saved ProjectWork files. Overwrites the selected file with current project.

Google Drive

Opens new tab with Google Drive.

Share file...

Opens Google Drive dialog to share file with others for editing or viewing. They can open to file in their Google Drive in folder Shared with me and edit or view the schedule in ProjectWork depending on how the file is shared. Edits are processed real-time to all shared schedules which are open, allowing for simultaneous collaboration.

Import > Microsoft Project XML file...

Loads an MS Project XML-file from the PC and converts it to a ProjectWork schedule. After the conversion, a link appears that opens the planning in a new tab.

Import > ProjectWork schedule from PC...

Loads a JSON file with ProjectWork schedule from the PC. After the loading, a link appears that opens the planning in a new tab.

Import > mindmap from PC...

Loads a JSON file created with MindMup from the PC and converts it to a ProjectWork schedule.
See From idea to schedule with mindmap for more details. After the conversion, a link appears that opens the planning in a new tab.

Project properties...

Opens a dialog with properties of the current project.


Post chat message...

Opens a popup dialog to post a message in a Google Chat space or Slack channel.
See Post chat message for more details.

Publish > schedule as HTML

Opens a dialog to publish the displayed schedule as preview or as HTML code. You can save the HTML code to a new file or overwrite an existing file.
See Publish schedule as HTML for more details.

Publish > schedule in Google Sheets

Opens a dialog to publish the schedule tasks and resources to a new or existing Google spreadsheet.
See Publish schedule in Google Sheets for more details.

Publish > milestones in Google Calendar

Opens a dialog to create, update and remove milestones in Google Calendar.
See Publish milestones in Google Calendar for more details.

Publish > sites in Google Maps

Opens a dialog to publish all Resources with Site filled-in in a .html file in Google Drive. This file can be viewed from Google Drive in Google Maps.
See Publish sites in Google Maps for more details.

Export > ProjectWork schedule to PC

Saves a ProjectWork schedule in a JSON file on the PC.

Export > Microsoft Project XML file

Exports the ProjectWork as MS Project XML-file to the PC.

Baselines...

Opens a dialog to set, show and compare baselines.

Report > project status...

Opens an HTML document with progress information on work hours. Includes the latest baseline if set as a reference.

Report > project inspection...

Opens an HTML document with information on how tasks and resources are assigned.

Report > dashboard...

Opens a dialog to add the project to a new or a selected dashboard or to update the project in the selected dashboard. See Report in dashboard for more details.

Print

Prints the tasks table and the Gantt chart via the browser as you see them. Adjust the mutual width of the panels and other viewing preferences, like hiding columns and collapsing tasks, before you print them. In Chrome print preview you can adjust the scale so that the entire planning is printed, possibly over several pages. In some browsers you can print to a PDF file.


New resource manager

Opens a new browser tab called ProjectWork-Resources. In this version of ProjectWork a resource manager can share its resources with multiple projects. Per project he can see to which tasks his resources are assigned to. Use Reload to see the last status since the schedule was opened.
See also Resource Management using ProjectWork.

Shared resources...

Shows which resource managers share resources with this project. The shared resources are grouped in the Resources sheet.

Reload

Reloads the schedule to show any changes in the shared resources since the schedule was opened.


Settings...

Opens a dialog with settings.

Working hours...

Opens a dialog to adjust the working hours for the project.

Non-working periods...

Opens a dialog to add or delete non-working periods to the project. A non-working period has a start date and a finish date. During the period the project is not executed for all resources and the schedule delays.


In-app purchase

After registration and selecting license type and period you can purchase the license with PayPal.

Manual

Opens this manual in new tab.

Helpdesk...

Opens contact form.

Adjust working hours

This dialog is opened from the ProjectWork menu.

A day can have 5 non-overlapping working periods. Default working hours: Monday - Friday (5 days) from 08:00 AM - 12:00 PM and 01:00 PM - 05:00 PM (2 periods). This accounts for 8 hours per day and 40 hours per week. Other examples of periods are in the table below for both AM/PM time display and the corresponding 24 hour display.

AM/PM   24 hour   duration
08:00 AM - 12:00 PM   08:00 - 12:00   4h
01:00 PM - 05:00 PM   13:00 - 17:00   4h
12:00 PM - midnight   12:00 - 24:00   12h
12:00 AM - midnight   00:00 - 24:00   24h

Change working periods by entering the new period times, checking the period(s) you like to change and clicking Apply.

Add working periods by setting the start and finish time of a period, checking 'new period' on the day(s) where you like to add the period and clicking Apply.

Remove working periods by leaving the period times empty, checking the period(s) you like to remove and clicking Apply.

Monitor schedule with baseline

This dialog is opened from the ProjectWork menu.

When you set a baseline, you make a copy of the schedule. The baseline is listed with the name you gave it together with the date and time it was made. Subsequent baselines follow in the list. You can permanently remove a baseline by deleting its name in the list and pressing the Apply button.

You can then select the baseline(s) you want to show. If selected, a baseline is shown below a task and resource in their tables, when the baseline corresponds.

You can compare a baseline with the schedule, using its value or the variance between baseline and schedule, also as a percentage.

Tasks

Tasks are the basis of the project schedule. They are the rows in a table with columns that contain properties of the tasks. They can be organized in a hierarchical breakdown structure with summary tasks.

The table can be shifted with the scroll bar at the the bottom or by "grabbing" the header with the mouse.

Coming to a complete schedule of tasks is best achieved in following steps:

  • Work Breakdown structure - the subdivision of an entire project into products and activities
  • Task order - the order in which tasks are depending on each other by linking them
  • Phases - groups of tasks that have a specific function like design, construction, delivery
  • Milestones - important decision moments concluding phases (in ProjectWork a task with duration 0)
  • Resources - people and means to complete the task
  • Work - the hours needed to complete a task
  • Start date - results with work, resources and available working hours in a finish date per task
  • Critical path - the linked tasks that result in the shortest project finish date
  • Documentation - information on design and progress

Table columns

Each task has the following fields with information, see also Arrange columns.


read-only

ID

Row sequence


read-only

WBS

Code indicating how the task fits in the breakdown. The Work Breakdown Structure (WBS) of a project shows how a project is build from products and activities.


required

Task description

Description of the task based on the product and/or activity needed to be delivered. In the details panel you can highlight a task description with a background color.


optional

Duration

The time a task takes in days (d) and hours (h), for example '2d 4h' corresponds to 20 hours. The default duration without unit is in days.
A duration of 0 turns a task into a milestone.


optional

Start date

Starting date and time of the task, according format from settings. Click to use the pop-up calendar to pick a date or enter date and/or time directly. Fast date entry is possible by skipping month and year giving the first date from today.


optional

Finish date

Finishing date and time of the task, according format from settings. Click to use the pop-up calendar to pick a date or enter date and/or time directly. Fast date entry is possible by skipping month and year giving the first date from today or start date.


optional, default 0%

Progress

Percentage indicating the completion of the task. In combination with progress indication at Settings the progress results in a color.

conditioncolor
today before task start dateno color
today after task start date and progress on schedulegreen
today after task start date and progress behind schedule yellow
today after finish date and progress less than 100%red
progress equals 100%no color

optional

Predecessors

The ID's of preceding tasks, see Link dependencies.


read-only

Slack

The time a task can start later before becoming part of the critical path. The time is in days (d) and hours (h), for example '2d 4h' corresponds to 20 hours.


optional

Resources

The abbreviation or name of assigned resources, see Assign resources to a task.


optional

Work

The total number of hours the assigned resources work to this task.


optional

Cost

Cost per task or the total cost of the assigned resources.


optional, default ASAP

Condition

ASAP = As Soon As Possible (empty is ASAP)
ALAP = As Late As Possible
Start = start on Start date
Finish = finish on Finish date


optional, default according Settings

Constant

Columns Resources, Work and Duration relate according: Work = Resources x Duration
Resources is the sum of the Resources of type Work: 3 for R1;R2[2]
When changing a column, one of the other two columns will change its value, depending on the Constant setting according to the table below.

constant change calculated change
Resources Resources
Work
Duration
Work = Resources x Duration
Duration = Work / Resources
Work = Resources x Duration
Work Resources
Work
Duration
Duration = Work / Resources
Duration = Work / Resources
Resources = Work / Duration
Duration Resources
Work
Duration
Work = Resources x Duration
Resources = Work / Duration
Work = Resources x Duration

You can select the default setting for new tasks in Settings > Default constant.


optional

Custom columns

Additional columns.

Dropdown menu

The tasks menu is at the top of the tasks panel and opens when clicked with the functions below.


Collapse

Collapses the selected summary tasks. If you want to keep and share this view, save it manually.

Expand

Expands the selected summary tasks. If you want to keep and share this view, save it manually.

Collapse level

Collapses all summary tasks with a WBS level equal to the selected task. If you want to keep and share this view, save it manually.

Collapse all

Collapses all summary tasks. If you want to keep and share this view, save it manually.

Show all tasks

Expands all summary tasks and shows all hidden tasks. If you want to keep and share this view, save it manually.

WBS and linked tasks

Shows selected task and all its preceding and succeeding tasks, including their summary tasks, if any. If you want to keep and share this view, save it manually.

Filter > critical path

Shows the tasks on the critical path. If you want to keep and share this view, save it manually.

Filter > unfinished tasks

Shows the tasks which are not 100% completed. If you want to keep and share this view, save it manually.

Filter > colored tasks

Shows the tasks which have a background color as highlight. If you want to keep and share this view, save it manually.

Filter > visible in Gantt chart

Shows only the tasks that are (partially) visible during the set timescale of the Gantt chart. If you want to keep and share this view, save it manually.

Sort down > on selected column

Sorts selected tasks downwards based on selected column.

Sort up > on selected column

Sorts selected tasks upwards based on selected column.


Increase indent

Increases the WBS level of the selected tasks if possible, e.g. 1.2 becomes 1.1.4.

Decrease indent

Decreases the WBS level of the selected tasks if possible, e.g. 1.3.1 becomes 1.4.

Insert rows above

Inserts above the selected rows as many empty rows as selected.

Insert rows below

Inserts below the selected rows as many empty rows as selected.

Erase rows

Erases the selected rows.

Delete rows

Deletes the selected rows.

Copy rows

Copies the selected row(s) onto the clipboard for further pasting.

Cut rows

Copies the selected rows onto the clipboard and then deletes them.

Paste rows

Inserts the clipboard at the selected row.

Paste options...

Opens a dialog to select what information to paste from the clipboard:
- per task any added color, note, documents in Google Drive, resources and links,
- custom columns from other schedule,
- how many times to repeat the clipboard (default is 1),
- how much to multiply the task duration (default is 1.0).

Save clipboard...

Opens a popup dialog, see Save tasks on clipboard.


Undo

Undoes the last change.

Redo

Redoes the last change.

Clear leveling selection

Clears all shifts of the selected task(s) due to assignment leveling.

Chain

Links the selected tasks sequentially.

Remove links

Removes all links from the selected tasks.

Columns...

Opens a dialog, see Arrange columns.

Link dependencies

Tasks may depend on each other for their execution order. This can be indicated with dependencies between tasks by referring to the IDs of the predecessors in the task column Predecessors. There are different types of dependency, which are placed behind the ID, see table below.

Type Link Dependency
FS Finish to Start The successor can only start when the predecessor finishes.
This is the default dependency if the type is absent.
SS Start to Start The successor can only start when the predecessor starts.
FF Finish to Finish The successor can only finish when the predecessor finishes.
SF Start to Finish The successor can only finish when the predecessor starts.

Tasks can be linked with the control key (Mac: meta key) and mouse click. Select the rows of one or more predecessors and then with Ctrl + Mouse click the successor. The predecessor(s) are linked with their ID in the Predecessors column at the successor. The link type is absent and FS by default, but another type can be added. Unlinking is done in the same way as linking, an existing link will be removed.

Each dependency can be adjusted by adding lag or lead time. Lag time introduces delay between the linked tasks, lead time introduces overlap between linked tasks. The lag/lead time is put after the dependency, where positive time is lag and negative time is lead.

Examples of dependencies:

3SS single Start to Start dependency with task ID 3
3SS;4 double dependency with tasks 3 and 4
3SS;4+1d lag time of 1 day with task 4
3SS;4-1d lead time of 1 day with task 4

Save tasks on clipboard

The clipboard is used to temporarily copy and paste tasks from and to all your schedules. Tasks on the clipboard can be saved and copied back to the clipboard later to be pasted into the schedule. The paste options determine the information to be pasted from the clipboard and the applied repetition and duration.

The contents of saved tasks cannot be edited afterwards. Saved tasks can be deleted after expanding them first. The order of multiple saved tasks can be changed into a logical order by dragging them. Both changes can be undone with Ctrl + Z.

The saved tasks can be copied as part of a schedule to a new schedule, ProjectWork dropdown menu > Make a copy... select option > include saved clipboard tasks. This allows the creation of a template schedule containing groups of tasks to be used by copied schedules as building blocks.

Gantt chart

The Gantt chart shows the schedule per task as a bar. The position of the bar depends on the timescale at the top. The timescale can zoom-in (+) and zoom-out (-) and the start date can be adjusted in a calendar.

When zoomed in, the Gantt chart can be shifted with the scroll bar at the bottom. As an alternative the timescale can be shifted by "grabbing" with the mouse. With the mouse in the timescale, the left mouse button zooms-in and the right mouse button zooms-out.

Gantt dropdown menu

The Gantt menu is at the top of the Gantt panel and opens when clicked with the functions below.


Selected tasks

Sets the timescale of the Gantt chart to match the earliest start date and the latest finish date of the selected task(s).
Tip: Select a summary task to see all its subtasks.

Today

Sets the start date of the Gantt-chart equal to today.

Project start

Sets the start date of the Gantt-chart equal to the project start.

Entire project

Shows the project from start to finish date.

Autofit

Sets the timescale to fit all visible expanded tasks.

Scale as Capacity chart

Makes the Gantt scale equal to the Capacity scale.


To Capacity chart

Changes panel view to show Capacity chart.

To Capacity with scale as Gantt

Changes panel view to show Capacity chart with scale equal to Gantt chart.

Resources

Resources are the people and the means necessary to perform a task. They are the rows in a table with columns that contain properties of the resources. They can be grouped into teams or clusters that summarize their properties.

The table can be shifted with the scroll bar at the the bottom or by "grabbing" the header with the mouse.

Table columns

Each resource has the following fields with information, see also Arrange columns.


read-only

ID

Row sequence


read-only

RBS

Code indicating how the resource fits in the breakdown of teams and clusters.


optional

Abbr

Abbreviation of this resource. If present, this abbreviation is used in column Resources in the Task table.


required

Resource name

Name of the person or description of the resource.


required, default Work

Type

List with possible resource types.


optional

Unit

Per hour, per piece, per meter, etc.


read-only

Progress

Percentage indicating the completion by the resource.


optional, default 1

Capacity

Maximum quantity of a resource above which the resource diagram shows red.
Also the quantity that is assigned to a task with Ctrl + Mouse click.


optional, default 0

Rate

Cost per resource unit.


read-only

Quantity

The total amount of units assigned of this resource.


read-only

Cost

Total cost of the resource.


optional

Account

Email address, Google account or code of a resource.


optional

Site

Resource location. A Google Maps icon appears to show the address.


optional

Custom columns

Additional columns.

Dropdown menu

The resources menu is at the top of the resources panel and opens when clicked with the functions below.


Collapse

Collapses the selected summary resource. If you want to keep and share this view, save it manually.

Expand

Expands the selected summary resources. If you want to keep and share this view, save it manually.

Collapse level

Collapses all summary resources with a WBS level equal to the selected resource. If you want to keep and share this view, save it manually.

Collapse all

Collapses all summary resources. If you want to keep and share this view, save it manually.

Show all resources

Expands all summary resources and shows all hidden resources. If you want to keep and share this view, save it manually.

Filter assigned tasks

Shows in the Tasks table the selected resource assigned tasks only, including underlying tasks. Other tasks are collapsed.

Sort down > on column

Sorts selected resources downwards based on column.

Sort up > on column

Sorts selected resources upwards based on column.


Increase indent

Increases the WBS level of the selected resources if possible, e.g. 1.2 becomes 1.1.4.

Decrease indent

Decreases the WBS level of the selected resources if possible, e.g. 1.3.1 becomes 1.4.

Insert rows above

Inserts above the selected rows as many empty rows as selected.

Insert rows below

Inserts below the selected rows as many empty rows as selected.

Erase rows

Erases the selected rows.

Delete rows

Deletes the selected rows.

Copy rows

Copies the selected rows onto the clipboard for further pasting.

Cut rows

Copies the selected rows onto the clipboard and then deletes them.

Paste rows

Inserts the clipboard at the selected row.

Paste options...

Opens a dialog to select what information to paste from the clipboard:
- per resource any added color, note, documents in Google Drive, resources and links,
- custom columns from other schedule.


Level all resources

Ensures that all assigned resources stay below their capacity by shifting forward tasks. In ProjectWork menu, item Settings under Resource leveling you can select what should be included in the leveling and where the result should be visible.

Clear all leveling

Shifts back all shifted tasks due to resource leveling. As a result resources may exceed their capacity, what can be seen as red in the Capacity chart.

Level selection

Ensures that selected resources stay below their capacity by shifting out tasks.

Clear leveling selection

Clears shifts of tasks assigned to selected resource(s) due to assignment leveling.


Undo

Undoes the last change

Redo

Redoes the last change

Columns...

Opens a dialog, see Arrange columns.

Assign resources to a task

Column Resources in the Tasks table shows per task the resources from the Resources table assigned to this task. Resource names are divided with a semicolon (;). The assigned quantity per resource is mentioned between square brackets ([ ]).

For example: R1;R2[2] means
1x R1
2x R2

If a resource has an abbreviation it will be used. If a resource is not in to the Resources table yet, it will be added.

Assigning resources is done easier by selecting one or more resources in the Resources table and by Ctrl + Mouse click a task in the Tasks table. The assignment of a work Type resource is done with a quantity equal to the Capacity, otherwise with a quantity of one. The quantity can be changed afterwards in the Resources column of the Tasks table.

Resource types

In the Resources table every resource has a type indication in the Type column. It affects how costs per resource are calculated per task based on its assignment and Rate.

Work Assigned per quantity and calculated per Work hour.
A full-time resource has a quantity of 1 (=100%).
A part-time resource has a quantity of less than 1.
A generic resource ('engineer') can have a quantity of more than 1.
The resource cost per task is calculated by multiplying the assigned quantity, total work hours and price per work hour.
Equipment Assigned per quantity and calculated per Duration hour.
The resource cost per task is calculated by multiplying task duration, the assigned quantity and price per hour.
Material Assigned per quantity to task. The optional Unit can be for instance 'meter'.
The resource cost per task is calculated by multiplying the number of assigned units and the cost per unit.
Part Assigned per quantity to task. The optional Unit can be for instance a part number.
The cost calculation is the same as for Material resource.
Service Assigned per quantity to task.
The cost calculation is the same as for Material resource.
Sprint Assigned to (summary) tasks to filter and summarize these tasks. A Sprint is a project in the Scrum framework. The Tasks table contains Product Backlog items with underlying work. To a sprint resource assigned items form a Sprint Backlog.
This type of resource accumulates costs, work hours and progress, but adds nothing to a task.
Owner Assigned to (summary) tasks to filter and summarize these tasks. This makes it possible to split costs across various owners.
This type of resource accumulates costs, work hours and progress, but adds nothing to a task.
Site Assigned to (summary) tasks to filter and summarize these tasks. This makes it possible to split costs per location. A site resource shows the address in the Site column by clicking on the Google Maps icon.
This type of resource accumulates costs, work hours and progress, but adds nothing to a task.

Capacity chart

The Capacity chart shows with an indication in time when a resource is active. For work resources the indication is a color relative to the set capacity:

  • blue if less than 50%,
  • red if more than 100%,
  • green in between.

Other type of resources will be shown grey. The position of the indication depends on the timescale at the top. The timescale can zoom-in (+) and zoom-out (-) and the start date can be adjusted in a calendar.

When zoomed-in, the Capacity chart can be shifted with the scroll bar at the bottom. As an alternative the timescale can be shifted by "grabbing" with the mouse. With the mouse in the timescale, the left mouse button zooms-in and the right mouse button zooms-out.

Capacity dropdown menu

The capacity menu is at the top of the capacity panel and opens when clicked with the functions below.


Today

Sets the start date of the Capacity-chart equal to today.

Project start

Sets the start date of the Capacity-chart equal to the project start.

Entire project

Shows the project from start to finish date.

Scale as Gantt chart

Makes the Capacity scale equal to the Gantt scale.


To Gantt chart

Changes panel view to show Gantt chart.

To Gantt with scale as Capacity

Changes panel view to show Gantt chart with scale equal to Capacity chart.

Settings

This dialog is opened from the ProjectWork menu.

Language

| English | Nederlands |

If the desired language is not listed, it is possible to translate ProjectWork in the Google Chrome browser with Google Translate. To do this, click on the Google Translate icon in the address bar. The dialogs regarding purchasing and the tables with project data will not be translated.

Number format

| 1,000.00 | 1.000,00 | 1 000,00 |

Thousands and decimal separator in number.

Currency

Selected currency symbol is shown where applicable.

Currency position

Position relative to amount.

Date format

| dd-mm-yyyy | dd.mm.yyyy | dd/mm/yyyy | mm/dd/yyyy | yyyy-mm-dd | yyyy.mm.dd | yyyy/mm/dd |

Order and separator (./-) for day (dd), month (mm), year (yyyy).

Time format

| hh:mm | am/pm |

24 hours or 12 hours.

Show time

Show only date or also time in table.

First day of week

Selection is visible in Gantt - and Capacity Diagram


Project summary (ID=0)

  • Show project summary in Tasks table and Gantt chart.
  • Show project summary in Resources table and Capacity chart.

Critical path indication

  • Indicate tasks in critical path in Start and Finish date columns with red.
  • Indicate tasks and links in critical path in Gantt chart with red.
  • Indicate Slack column value in Gantt chart with dotted bar.

Progress indication

  • Indicate progress color in column Progress in Tasks table.
  • Indicate progress color in bar in Gantt chart.

Resource leveling

  • Include/exclude tasks from the past in the leveling.
  • Include/exclude completed tasks in the leveling.
  • Indicate shifted task in the Tasks table.
  • Indicate shifted task in the Gantt chart.

Default condition

| As soon as possible | As late as possible | Start on date | Finish on date |

Default condition for new task.

Default constant

| Resource | Work | Duration |

Default constant for new task.

Google Drive

Google Drive is an online storage service. ProjectWork saves schedule file edits automatically in the Google Drive of the user after each schedule change made. A simultaneous user of the same file will also see the change. To avoid disturbance between users of the same schedule file, changes in the view of the schedule are not saved automatically. Changes in view can be saved manually when needed and a simultaneous user of the same file will then see the changed view. To gain access to Google Drive, the user must give a one-time permission to ProjectWork if requested. Stored ProjectWork files can be opened from the ProjectWork app or from the Google Drive website.

Start a new project in Google Drive

A new ProjectWork file can be created and opened by pressing the Create button in Google Drive and selecting ProjectWork as application.

Open existing project in Google Drive

An existing file can be opened in ProjectWork by double clicking on a ProjectWork file or by right-clicking on a file and selecting Open with... > ProjectWork.

Setting ProjectWork as the standard application for .json files can be achieved in the settings menu (gear icon) under Manage apps.

The ProjectWork icon appears in front of the file name and ProjectWork opens with this file.

Collaboration

With ProjectWork a team can collaborate on a shared project schedule. When they do this at the same time, they see each others changes. The number of participants is indicated before the file name in the ProjectWork panel. To know where the modification took place there is the option to mark this. This option is default on.

Collaboration on a schedule can start after following steps in Google Drive:

  1. Create a new ProjectWork schedule or use an existing one
  2. Select the file and right click to go to Share in the context menu
  3. Add participants and their access rights in the Share popup
  4. The participating accounts open the file in their 'Shared with me' folder in Google Drive

Apps integration

ProjectWork has functions that provide information to other apps. To gain access to these apps, the user must give a one-time permission to ProjectWork if requested.

Post chat message

This dialog is opened from the ProjectWork menu.

You create a webhook URL once for a Google Chat space or Slack channel and save it via this dialog. A link to the opened planning is added per message. You can specify the view of this planning so that when you open the link in the posted message, this view is shown. You can also add information, such as the project description, to the message. Finally, you write a text and post the message in the Google Chat space or the Slack channel.

The text can be formatted: *bold*, _italics_ and <link> or <link|text>.

Publish schedule as HTML

This dialog is opened from the ProjectWork menu.

The published HTML code exactly matches the task table and the Gantt diagram: collapsed tasks and hidden columns are not published. The Gantt diagram is shown in its entirety, from the beginning to the end of the project. The HTML code is visible as a preview in the browser and as code to be embeded into a website, for example in Google Sites. The HTML code can also be stored in Google Drive.

See example.

Publish schedule in Google Sheets

This dialog is opened from the ProjectWork menu.

The schedule can be published as a new spreadsheet or as an update to a previously published spreadsheet. The spreadsheet consists of two worksheets: Tasks and Resources. The Tasks worksheet features a Gantt chart on the right side. Above the header row is room to add custom text or calculations.

The order of columns can be changed and columns can be hidden or deleted. Deleted columns are not added again with an update. Custom columns can be inserted containing information or cell formulas that use the planning data. You can also add custom worksheets with diagrams that use the planning data.

An update synchronizes the spreadsheet data with the tasks in the schedule. Added formatting to the spreadsheet, such as colors, and added comments are retained. The Gantt chart, dependent columns, calculations and charts are updated. For example, the update enables reporting on the current schedule, such as a comparison with the baseline schedule, see Frequently asked questions.

Publish milestones in Google Calendar

This dialog is opened from the ProjectWork menu under Publish.

A milestone is a task in the schedule with a duration of 0. Published milestones appear in private calendar 'ProjectWork' of the signed in Google account. This calendar may contain milestones of other published ProjectWork schedules of the same account.

Resource(s) assigned to a milestone which have their Account filled-in in the Resources table will get this milestone in their Google calendar(s).

Changes to milestones in the schedule are updated in the 'ProjectWork' calendar and in the calendars of resources with a Google account when your re-publish.

See example.

Publish sites in Google Maps

This dialog is opened from the ProjectWork menu under Publish. Publishing results in a link to a dynamic map showing the locations of resources. By clicking on the location, information about the associated resource appears, costs and notes are optional when published.

The link can be posted on a site or e-mailed. Re-publication gives the same link, but with the latest information. The link can also be removed.

See example.

Report in dashboard

This dialog is opened from the ProjectWork menu.

The dashboard is a common spreadsheet to track all projects. The projects are listed row by row with information and status per column. For each project there is a bar on the right of the same row from start to end date with the progress. You can insert joint columns for additional information and statistics. Each project updates the information itself. You can insert this spreadsheet into a Google site.

You start reporting by selecting a spreadsheet that has already been created as a dashboard using the Select button or you first create a new dashboard with the New button. In both cases, the dashboard is saved and shown as a link. With the link you open the spreadsheet with the dashboard. With the Update button you update the dashboard with the latest information. The account that updates the project and the moment when is listed with the project.

Selecting a dashboard is only possible if the dashboard is shared with your account. A project added to a selected dashboard is added below the present projects. You can change the order by dragging a row with a project. A project that no longer needs to be in a dashboard can be removed from the spreadsheet.

The dashboard spreadsheet can be adjusted to your liking. Columns can be removed without coming back after updating. Column headers can be adjusted, the order of columns can be changed. Formatting is retained after updating the data.